yb鸭脖体育在线

  • <tr id='aej7'><strong id='a30s'></strong> <small id='c6s2'></small><button id='bpspfs'></button><li id='31axqy'> <noscript id='jfgb'><big id='qyqm'></big><dt id='52o3qu'></dt></noscript></li></tr> <ol id='v4rwad'><option id='7z6q'><table id='ps02z'><blockquote id='byrf3'> <tbody id='ikbjf'></tbody></blockquote></table></option></ol><u id='nhth3'></u><kbd id='y46nf'> <kbd id='xgykp'></kbd></kbd>

    <code id='7o29h'><strong id='hcsgo'></strong></code>

    <fieldset id='d93j'></fieldset>
          <span id='b6y8'></span>

              <ins id='tmxj'></ins>
              <acronym id='60dm'><em id='2bb4'></em><td id='5np8qj'><div id='onwkt'></div></td></acronym><address id='n45l'><big id='wegmm'><big id='mim1'></big><legend id='h93s7s'></legend></big></address>

              <i id='lvldaf'><div id='jvidcc'><ins id='guw5v'></ins></div></i>
              <i id='8yy1u'></i>
            1. <dl id='hbz6'></dl>
              1. <blockquote id='3e6s7'><q id='38b98b'><noscript id='v4qb'></noscript><dt id='m2sy'></dt></q></blockquote><noframes id='1qmp1'><i id='psapfl'></i>
                欢迎来到宁夏yb鸭脖体育在线房地产开发有限责任公司网站!
                当前位置:施工动态

                “丰泽美居”项目工程建设情况

                信息来源:          发布日期:2020-10-21

                截止目前现场进展情况如下:

                1、1#-18#住宅楼外墙保温板及装饰线条已完成,外墙漆完成40%、楼梯间地砖开始施工,门厅干挂石材、预埋件及主龙骨完成70%。住宅楼给水完成,排水完成95%,消防完成80%,电信有线电视完成,智能化楼内穿线已完成,西区地暖敷设80%、东区地暖敷设90%。

                2、19#-24#营业房屋面施工基本完成,墙体抹灰完成70%,室内腻子50%25#楼完成室内腻子基本完成,消防水池完成防水层及保护层。

                3、东、西区给排水完成室外土方开挖填、预制井砌筑、安装(井盖未安装)完成80%;给水管、排水管、消防管的敷设完成80%,西区化粪池100方。直饮水室内安装完成50%。

                4、26#、27#地库完成顶板回填土、强排管连接;地库内完成85%暖管安装、消防喷淋、通风、照明灯线安装基本完成。

                5、西区:3#、11#楼北侧宅前道铺装完成,6#楼西北景墙主体完成,西区西围墙抹灰完成;东区大门水景挡土墙基础浇筑完成,廊架水景基础浇筑完成14#、17#楼宅前道铺装13#-14#楼之间园路铺装完成。迎客松及部分树木进场栽植。

                6、中水池工程进度:中水池浇主体完成,1#、5#雨水池主体钢筋模板完成,2#雨水池基础筏板钢筋模板完成